Bechtel Group, Inc.
Bechtel Group, Inc.
P.O. Box 3965
San Francisco, California 94119
U.S.A.
(415) 768-1234
Private Company
Incorporated: 1925
Employees: 25,000
Sales: $6.8 billion
One industry analyst has noted that Bechtel’s achievements as the largest United States construction and engineering firm have reshaped more of the earth’s landscape than virtually any other human efforts in history. As a private and predominantly family-controlled company, Bechtel has long been averse to publicity, an attitude which has sometimes been problematic in light of the firm’s numerous links to prominent U.S. government officials. Although as a private company Bechtel is not required to publish financial information about its operations, 1985 estimates suggest the company generated $8.6 billion in revenues.
Most of Bechtel’s business comes from building traditional electric utility plants, although the company has also played a key role in the development of the domestic and foreign nuclear power industries. The downturn in the economy during the early 1980’s, and the concurrent recession in energy-related industry, compelled Bechtel to consolidate its operations by reducing the workforce, diversifying into areas outside its traditional markets, contracting jobs previously considered too small, and providing operating services for existing power plants.
In 1884 when he was 12 years old, Warren A. Bechtel moved with his family from a farm in Illinois to the frontier area of Peabody, Kansas. After graduating from high school, Bechtel ventured unsuccessfully into a music career. When “The Ladies Band” failed, Bechtel’s father wired return fare to the stranded slide trombonist. The disappointed musician went back to work on the family farm. Some years later poor farming conditions left Bechtel virtually without any possessions other than a team of 14 healthy mules. When the Chicago Rock Island and Peoria Railway Company pushed westward in 1889, Bechtel gathered up his mule team and worked his way across the continent grading railbed for frontier train lines.
Bechtel eventually sold his mule team, but he continued working for the rail industry in a variety of manual labor positions. He managed to accumulate a small fortune and formed the W. A. Bechtel Company with his three sons and his brother. The young company began many new ventures, including construction of the Northern California Highway and the Bowman Dam, which was at the time the second largest rock-fill dam in the world. By the time the company incorporated in 1925, Bechtel was the largest construction firm in the Western U.S. When a six-company consortium received the $49 million contract for construction of the Hoover Dam, Warren Bechtel became president of the group. Work on the enormous dam lasted from 1931 to 1936. Warren Bechtel did not live to see the project completed, however; he died suddenly in 1933 at age 61.
Stephen Bechtel, one of the founder’s three sons, took over the presidency in 1935. He had previously been a vice president. The young executive directed the company to new financial and industrial heights, supervising completion of the Hoover Dam as well as work on the San Francisco-Oakland Bay Bridge, a hydrogeneration plant, and the Mene Grande Pipeline in Venezuela.
As the United States entered World War II, an already established partnership between Bechtel and John McCone, a steel salesman, grew to encompass a syndicate of companies participating in the construction of large shipyards. McCone and Stephen Bechtel had met at the University of California and had become business associates during work on the Hoover Dam. As an employee of Consolidated Steel, McCone secured the supply of necessary support structures for Bechtel. The business association proved so successful that after the dam was finished the former classmates formed a partnership. By 1940 McCone secured contracts for the partnership to build ships and tankers, and to modify aircraft for the war effort. Later the partnership developed the syndicate that built the Calship and Marinship yards in California, as well as a total of 500 ships. When McCone took a postwar position as undersecretary of defense, it was revealed that the directors of Calship earned 440 times their initial investment of $100,000-a profit of $44 million.
Bechtel’s operations continued to expand in the years following the war. The 1100-mile Trans-Arabian Pipeline, completed in 1947, is regarded as the first major structure of its kind. The South Korean Power Project effectively doubled that nation’s energy output in one move. In 1951 the pioneering company developed the first electricity-generating nuclear power plant, in Arco, Idaho. Later the company built a nuclear fuel reprocessing plant there. By the end of the 1950’s Bechtel had construction and engineering projects on six continents and was ready to take advantage of the emerging market for nuclear power.
In 1960 Stephen Bechtel became chairman of the board, and Stephen Jr., a Stanford Business School graduate and grandson of the founder, stepped into the chief executive officer post. A 1978 estimate suggested that the two men controlled at least 40% of company stock. In the likely event of the younger Stephen one day inheriting his father’s wealth, it is estimated that he could become the richest person in the U.S. (The other 60% of Bechtel stock is held by some 60 top executives who have agreed to sell back their shares when they leave the company or die.)
With a new generation of leadership in place, the company sought to gain hegemony in the emerging nuclear power industry. In 1960 Bechtel completed the nation’s first commercial nuclear station, in Dresden, Illinois. Two years later the company built Canada’s first nuclear power plant. Construction in foreign markets began to increase almost immediately thereafter. Although the nuclear power industry subsequently ran into difficulties such as cost overruns, questions about environmental safety, and stiff regulatory measures, Bechtel still continues to promote nuclear energy as a necessary option to conventionally generated power.
Bechtel’s construction projects in the 1960’s and 1970’s included the San Francisco Bay Area Rapid Transit system (BART), the subway transit system in and around Washington, D.C., a slurry pipe in Brazil, and an innovative tar sands project in Alberta, Canada.
In the 1970’s two former Nixon cabinet members took executive posts at the company. Later both men, George Shultz and Caspar Weinberger, would leave Bechtel for positions in the Reagan Administration. Bechtel has actively cultivated its ties to the federal government, and employs several former high officials—a fact which bothers critics of the company.
In 1976 Bechtel unveiled plans for its Jubail Project, the largest undertaking ever attempted by a construction company. On Saudi Arabia’s Persian Gulf coast, the company is building a futuristic industrial community on the site of an ancient fishing village. The project is expected to be completed in 1996 at an estimated cost of $100 billion. The new city will be the home of Saudi Arabia’s integrated petrochemical industry. A 1973 meeting between Stephen Bechtel, Jr. and King Faisal was the catalyst for the plan to haul off 370 million cubic meters of sand and build a modern city complete with a five-million-gallon desalination plant, modular homes, a sex-segregated swimming marina, and a number of factories.
Due in part to a broad political effort aimed at halting the use of nuclear power in the U.S., in recent years the company has had to turn away from nuclear energy to less controversial markets. However, problems in the nuclear power industry persist. A 1978 lawsuit concerning malfunctions at the Palisades nuclear generator in Michigan cost Bechtel $14 million in settlement fees. In addition, a 1984 Mother Jones magazine article suggested that in attempting to secure nuclear power contracts in South Korea the company may have violated the 1977 Foreign Corrupt Practices Act through the use of irregular payments. The article also argued that certain Bechtel executives who later became top U.S. government officials may have known the payments warranted investigations by the Federal Bureau of Investigation and the Justice Department but said nothing. (The company issued its employees a point-by-point rebuttal of the article.)
The company was in the limelight several times during he 1970’s. A 1972 class-action suit alleging sex discrimination at Bechtel settled out of court for $1.4 million. A bribery scheme involving construction of a New Jersey pipeline led to convictions for four Bechtel employees. Further unwanted publicity arose from the revelation that Bechtel had installed a 420-ton nuclear-reactor vessel backward. Finally, in 1975 the U.S. Justice Department sued Bechtel for allegedly participating in an Arab boycott of Israel, a charge the company denied.
The decade was also a turning point for Bechtel’s traditional business in construction and engineering. Prompted by increased government regulation and changing economic conditions, Bechtel embarked on a new program of financing and operational services. Soon after they began, the new divisions contributed 66% of total revenues. To defray increasing construction costs, the company now secures financing for its customers, and in some cases even puts up its own money. Bechtels diversification program also included acquiring a 15% share of the Peabody Coal Company and a major interest in the prestigious Dillon, Read & Company investment firm. By 1982 over half the company’s business involved overseas markets.
During the Reagan presidency Bechtel’s ties to the federal government increased considerably. Shultz left the presidency of Bechtel Corporation to become Secretary of State after Alexander Haig, former chairman of United Technologies, left the post in 1982. Weinberger, previously the Bechtel general counsel, was Secretary of Defense for the first seven years of the Reagan administration. By 1984 Bechtel’s connections in Washington also included CIA director William Casey, Middle East special envoy Philip Habib and former CIA director Richard Helms, all of whom had worked for the company either as employees or as consultants in the past.
Stephen Bechtel, Jr. is now chairman of the board. Alden P. Yates, Bechtel president, has led the firm into numerous projects previously regarded as too small for Bechtel. These include finishing jobs abandoned by the company’s competitors and actively seeking contracts, even those as small as $2 million. Furthermore, remodification and modernization efforts at existing plants offset the lack of contracts for new construction. Finally, the company’s operating services division keeps skilled experts at work in their fields, mostly in ongoing maintenance of existing facilities. Despite measures to locate new sources of income, Bechtel had to cut its workforce in 1984 to 35,000 (from 45,000 in 1982).
With new Bechtel offices open in New Delhi and Beijing, and a large amount of construction underway in the Pacific Basin, industry analysts predict that in the future approximately 70% of the company’s business will be abroad. While Bechtel consolidates its business and enters new markets, it continues to maintain an impressive presence within the international construction industry.
Principal Subsidiaries
Bechtel Western Power Corp.; Bechtel Eastern Power Corp.; Bechtel Inc.; Bechtel National, Inc.; Bechtel Limited; Hydro & Community Facilities Division. The company also has subsidiaries in Argentina, Australia, Brazil, Canada, Chile, China, Egypt, France, Indonesia, Korea, Saudia Arabia and Spain.
Further Reading
The Bechtel Story: Seventy Years of Accomplishment in Engineering and Construction, San Francisco, The Company, 1968.