NRC BEGINS SPECIAL INSPECTION AT JAMES A. FITZPATRICK NUCLEAR PLANT

From: Regulatory Intelligence Data | Date: July 5, 2005| Author: | Copyright information

INDSTRY GROUP 99
Regulatory Intelligence Data
07-05-2005
The Nuclear Regulatory Commission has initiated a special inspection
at the James A. FitzPatrick nuclear power plant in response to the discovery
of cracking in the facility's torus, or pressure suppression chamber, and
a shutdown cooling line. Members of the three-person team arrived this
afternoon at the Scriba, N.Y., plant, which is operated by Entergy.
Among the objectives of the special inspection in the short term will
be to review the adequacy of Entergy's initial evaluations of the cause,
the company's assessment of whether any ...

Related newspaper, magazine, and trade journal articles from HighBeam Research

(Including press releases, facts, information, and biographies)

Kewaunee plant faces scrutiny again; Nuclear agency says start-up procedures were not followed
; ...Kewaunee nuclear plant is under extra...Friday launched a special inspection at the single-reactor plant east of Green...procedures during the plant's start-up on...launch of the special inspection doesn't prevent...restarting the plant, agency spokeswoman...report on ...
Kewaunee plant faces scrutiny again: Nuclear agency says start-up procedures were not followed.
; ...Kewaunee nuclear plant is under extra...Friday launched a special inspection at the single-reactor plant east of Green...procedures during the plant's start-up on...launch of the special inspection doesn't prevent...restarting the plant, agency spokeswoman...report on ...
NRC BEGINS SPECIAL INSPECTION OF ELECTRICAL PROBLEMS AT THE POINT BEACH NUCLEAR PLANT
; ...Commission has begun a special inspection at the Point Beach Nuclear...an Unusual Event. The plant, owned by FPL Energy...was terminated. The plant was in a stable condition...event. NRC staff at the plant and in the Region III...units of the point Beach plant remain in a stable ...
NRC BEGINS SPECIAL INSPECTION OF ELECTRICAL PROBLEMS IN SHUTDOWN AT D. C. COOK NUCLEAR POWER PLANT
; ...Regulatory Commission has begun a special inspection of electrical problems at the...the automatic shutdown of the plant's Unit 2 on Tuesday, Nov. 8...administrator. "We've sent the special inspection team to better understand the...
NRC BEGINS SPECIAL INSPECTION OF PUMP ISSUE AT THE POINT BEACH PLANT
; ...Commission has begun a special inspection at the Point Beach Nuclear...with a pump that led to a plant shutdown on June 14. The...operating limit. As a result, plant operators stopped the...problem and fix it. However, plant operators were unable...the problem causing the plant to ...
NRC BEGINS SPECIAL INSPECTION AT THE PALISADES NUCLEAR POWER PLANT DUE TO OPERATIONAL
; ...is conducting a special inspection at the Palisades...containment area. The plant is operated by...problems. The special inspection will also evaluate the plant's ability to manage...shutdown. The special inspection will also review...
NRC SPECIAL INSPECTION INTO CAUSES OF REACTOR SHUTDOWN AND ASSOCIATED EQUIPMENT PROBLEMS AT CLINTON
; ...has begun a special inspection into the circumstances...response of some plant equipment...dispatched a special inspection to the plant to better...the Clinton plant. The report...close of the special inspection. The report...
Kewaunee managers commit to changes; They assure regulators on nuclear plant safety
; ...of the Kewaunee nuclear plant told federal regulators...committed to improving the plant's performance, after a special inspection early this year revealed...revealed problems at the plant, particularly in the area...runs the plant. During a special meeting Wednesday at ...
NRC: Plant's safety risk is human error.
; ...Oyster Creek nuclear power plant operated safely last year...Commission brought up a special inspection -- stemming from a 2005 violation -- the plant still needs to pass and...could seriously jeopardize plant safety, NRC spokesman...long-lasting reform, he said. The plant's ...
NRC DISPATCHES SPECIAL INSPECTION TEAM TO LOOK INTO SAFETY INJECTION PUMP PROBLEM AT KEWAUNEE
; ...Commission has begun a special inspection into the clogging of the...Kewaunee Nuclear Power Plant in Kewaunee, Wisconsin...Management Company. The plant was shut down on January 16, when routine testing by plant staff uncovered that the...emergency cooling at the plant. This problem ...